Project description

Reconditioning of an existing commercial premises to open the new Thinking Barcelona store.

  • Thinking Barcelona store located in terminal 2 of Barcelona-El Prat Airport.
  • Refurbishing of existing commercial premises. The construction work that took place included paving, installations, roof, facade and structural reinforcements. Tasks on structural reinforcements caused a delay of two weeks in the execution of the construction work, since they were not planned. Despite this, the store was able to open a week earlier than expected.
  • The project lasted seven weeks, ending on May 20, 2018.
  • In November 2018, it was decided to install decorative vinyl on all the front walls of the wall units. Initially the furniture had a gloss white finish.

Comprehensive management of the entire project within the general airport regulation and in compliance with Barcelona-El Prat Airport requirements. Process of permits, certificates and licenses with the local authorities.

Client

Dufry

Sector

Commercial

Services provided

Project Management

Year of completion

2018